§ 5.00. Soil cement stabilized base course.


Latest version.
  • 5.01.
    The testing laboratory shall perform the inspection tests and services set out in paragraphs 5.02 through 5.07.

    5.02.
    Preliminary soil profile of all streets and the establishment of control factors to be used during processing.

    5.03.
    The placement of inspectors on the site of operations at all times during operations. The number of inspectors will vary with the magnitude of the project; however, sufficient personnel shall be available at all times so as not to delay contractor and to keep abreast of job progress.

    5.04.
    Checking the percent of cement used and specified, depth of treatment, pulverization of material, moisture control and checking compaction operations.

    5.05.
    The conducting of field density tests in sufficient number with dispatch and promptness.

    5.06.
    The rendering of daily reports showing complete details of operations and location of activities.

    5.07.
    All tests and inspections to be in accordance with specifications and recommendations of the Portland Cement Association on this subject.